Wednesday, November 30, 2011

Continued Discussion about 787

Since I was told to elaborate more on the Dreamliner 787 history, I feel very obligated to do so because hopefully it will satisfy me and my follower(s). First thing first, Here is a little HISTORY trivia about the Boeing 787. The 787 program was launched in April 2004 with a record order from All-Nippon Airways. Since that time, 57 customers from six continents of the world have placed orders for 821 airplanes valued at about $145 billion, making it the most successful twin-aisle launch of a new commercial airplane in Boeing's history. The 787 program opened its final assembly plant in Everett in May 2007. First flight of the 787 Dreamliner occurred on December 15, 2009.More than 50 of the world's most capable top-tier supplier partners are working with Boeing to bring innovation and expertise to the 787 program. The suppliers have been involved since the early detailed design phase of the program and all are connected virtually at 135 sites around the world. First delivery of the 787 to ANA is scheduled for September of 2011.
On September 5, Boeing announced a three-month delay, blaming a shortage of fasteners as well as incomplete software.On October 10, 2007, a second three-month delay to the first flight and a six-month delay to first deliveries was announced due to problems with the foreign and domestic supply chain, including an ongoing fastener shortage, the lack of documentation from overseas suppliers, and continuing delays with the flight guidance software. Less than a week later, Mike Bair, the 787 program manager was replaced. On January 16, 2008, Boeing announced a third three-month delay to the first flight of the 787, citing insufficient progress on "traveled work". On March 28, 2008, in an effort to gain more control over the supply chain, Boeing announced that it planned to buy Vought Aircraft Industries' interest in Global Aeronautic; the company later agreed to also buy Vought's North Charleston, S.C. factory.

During the late 1990s, Boeing began considering replacement aircraft programs as sales for the 767 and Boeing 747-400 slowed. The company proposed two new aircraft, the 747X, which would have lengthened the 747-400 and improved efficiency, and the Sonic Cruiser, which would have achieved 15% higher speeds (approximately Mach 0.98) while burning fuel at the same rate as the existing 767. Market interest for the 747X was tepid, but the Sonic Cruiser had brighter prospects. Several major airlines in the United States, including Continental Airlines, initially showed enthusiasm for the Sonic Cruiser concept, although they also expressed concerns about the operating cost.The global airline market was upended by the September 11, 2001 attacks and increased petroleum prices, making airlines more interested in efficiency than speed. The worst-affected airlines, those in the United States, had been considered the most likely customers of the Sonic Cruiser, and thus Boeing officially cancelled the Sonic Cruiser on December 20, 2002. Switching tracks, the company announced an alternative product using Sonic Cruiser technology in a more conventional configuration, the 7E7, on January 29, 2003. The emphasis on a smaller mid-size twin-jet rather than a large 747-size aircraft represented a shift from hub-and-spoke theory towards the point-to-point theory, in response to analysis of focus groups.

The replacement for the Sonic Cruiser project was dubbed the "7E7"(with a development code name of "Y2"). Technology from the Sonic Cruiser and 7E7 was to be used as part of Boeing's project to replace its entire airliner product line, an endeavor called the Yellowstone Project (of which the 7E7 became the first stage). Early concept images of the 7E7 included rakish cockpit windows, a dropped nose and a distinctive "shark-fin" tail. The "E" was said to stand for various things, such as "efficiency" or "environmentally friendly"; however, in the end, Boeing claimed that it stood merely for "Eight". In July 2003, a public naming competition was held for the 7E7, for which out of 500,000 votes cast online the winning title was Dreamliner. Other names in the pool included eLiner, Global Cruiser and Stratoclimber. Boeing had originally planned for a first flight by the end of August 2007 and premiered the first 787 at a roll-out ceremony on July 8, 2007, which matches the aircraft's designation in the US-style month-day-year format (7/8/07). However, the aircraft's major systems had not been installed at that time, and many parts were attached with temporary non-aerospace fasteners requiring their later replacement with flight fasteners. Although intended to shorten the production process, 787 subcontractors initially had difficulty completing the extra work, because they could not procure the needed parts, perform the sub assembly on schedule, or both, leaving remaining assembly work for Boeing to complete as "traveled work".

On April 9, 2008, Boeing officially announced a fourth delay, shifting the maiden flight to the fourth quarter of 2008, and delaying initial deliveries by around 15 months to the third quarter of 2009. The 787-9 variant was postponed to 2012 and the 787-3 variant was to follow with no firm delivery date. On November 4, 2008, the company announced a fifth delay due to incorrect fastener installation and the Boeing machinists strike, stating that the first test flight would not occur in the fourth quarter of 2008. After assessing the 787 program schedule with its suppliers, Boeing confirmed on December 11, 2008 that the first flight would be delayed until the second quarter of 2009.

psi (102.7 kPa) differential, which is 150 percent of the maximum pressure expected in commercial service (i.e., when flying at maximum cruising altitude). In December 2008, the Federal Aviation Administration (FAA) passed the maintenance program for the 787.

On May 3, 2009, the first test 787 was moved to the flight line following extensive factory-testing, including landing gear swings, systems integration verification, and a total run-through of the first flight. On May 4, 2009, a press report indicated a 10–15% range reduction, about 6,900 nmi (12,800 km) instead of the originally promised 7,700 to 8,200 nmi (14,800–15,700 km), for early aircraft that were about 8% overweight. Substantial redesign work was expected to correct this, which would complicate increases in production rates;Boeing stated the early 787-8s would have a range of almost 8,000 nmi (14,800 km). As a result, some airlines reportedly delayed deliveries of 787s in order to take later planes that may be closer to the original estimates. Boeing expected to have the weight issues addressed by the 21st production model.

As of today, 851 orders of Boeing 787 Dreamliners are confirmed on books. Imagine the oppertunities that they will create for all of us....?